Monday 24 February 2014

The Vision Pratumnak Hill Pattaya construction update 25 February 2014

The Vision - Construction update as 25 February 2014
Structure work 96.820%
Architecture and Finishing work 28.349%
Electric System works 39.536%
Sanitary System Works 49.859%

Construction expected to be completed Q4 2014


Photograph shows the lift core and column on 23rd floor

Private RE-SALE condominium can be viewed at: http://www.fivestarvillasandcondos.com/Property/Condominium-For-Sale-Pratumnak--Re-Sale-11736

Please call Robert on 08 1938 8391 for more details or a site visit

No comments:

Post a Comment