Developer update | 7 January 2012
"You may
recall that we were having a couple of issues with the IEE application.
The biggest
problem that we faced was that they were reporting the road to be only 6 meters
wide and so this would cause a problem with the licensing.
The main
fault here was that they were relying on city hall documentation which in our
case was very old and so not updated since the road was widened!
Well we
have been focusing hard on that and to cut a long story short, we finally
managed to get the road professionally measured and updated.
The road is
way and above the required width and so now we are finalising the application
paperwork and the full prospectus will be submitted very shortly.
We have
been told now to expect this process to take 45-60 days and so this is finally
good news but due to the above we have had to extend our scheduled start date
to be the end of March and the completion date for the end of 2014.
A couple of
changes that I would like to inform you about:
There are
slight changes to some room sizes, and in particular the top floor corner one
bedroom is now a very attractive 60m.
Also the
Ground Garden Floor units are smaller (= cheaper and more affordable) and the
previous water features have now been changed to ‘Tropical Garden’ (as
apparently water is not natural enough to be considered as an environmental
benefit!)
For prices please see: http://www.fivestarvillasandcondos.com/en/Property/Location/Thailand/Wong%20Amat%20Beach/Condo/5451/Condominium-for-sale-Wong-Amat-SIXTYTHREE@12?DisplayType=Default
No comments:
Post a Comment