Update 22 June 2012
All piling works are complete
for Towers A and B.
The highly-experienced
contractor, K Tech Public Company Limited, mobilized at the site at the end of
April 2012.
All concrete and steel tests
were completed in May and boundary lines for both Towers were set.
On June 1st 2012 K Tech commenced structural work on The
Peak Towers and began pouring the foundations for Tower A.
This process will continue for the next 2 months, with
foundations for both Towers A & B set to complete by August 2012.
For availability and best prices call Robert on 08 1938 8391
Photograph taken 22 June 2012